The Reichstag at night 
Building work  
Conversion work started: July 1995
Structural work: March 1996 – June 1998
Topping out: 18 September 1997
Interior work: March 1998 – April 1999
Completion: April 1999
Handed over: 19 April 1999

Technical details
 
Volume of the building: about 400,000 m³
Main floor area: about 11,000 m²
Usable floor space: 61,200 m²
Height: 47 m
Amount of concrete used in rebuilding: 20,000 m³
Area of the debating chamber: 1,200 m²
 
The Dome:
 
Height: 23.5 m above the roof terrace
Height of the viewing platform: 40.7 m
Highest point above street level: 47 m (including dome)
Diameter: 40 m
Steel used: 800 t
Glass: 3,000 m²
Number of mirrors in the cone: 360

 
www.bundestag.de/bau_kunst/bauwerke/loebehaus/index.html
www.bmvbs.de/Bauwesen/Bauherr-Bund-,1509.904098/Paul-Loebe-Haus.htm

 
The BBB's projects
Planning history
The basic architectural concept from a city planning point of view
A historic shell covering a hi-tech heart
The dome - a spell in glass and steel